Logo Procetradi
Client: Electro Oriente
Date: 2017

We carried out the implementation of 10 power substations and implemented a communications system with carrier wave, radio links and fiber optics.

This project involved the implementation of the 24x7 Control Center for the automation, monitoring and integral control of the power substations and the commissioning of a redundant ADMS system with SCADA, DMS, OMS and ICCP modules. In addition, it included the supply, development and engineering, integration, installation, commissioning and on-site testing of the SCADA System.

This project optimizes the operational and commercial management of Electro Oriente and improves the quality of the electricity supply for the department of San Martín.